Campus Solutions Upgrade Scheduled for June

Friday, April 8th, 2011

Campus Solutions is the student-oriented component of our MaineStreet application suite. It is scheduled for a long-planned upgrade this June 7th.

ITS’ Administrative Systems Development and Support has been working towards this goal for over a year to allow UMS to continue to provide the best services and products to the Students, Faculty, and Staff. We all look forward to the roll-out of this latest upgrade this summer.

New UMS CA Certificate Available for Download

Tuesday, January 19th, 2010

The University of Maine System issues self-signed certificates for use with some of the applications and websites that we use and host. No certificate lasts forever, including those of Certificate Authorities. Our own old (CA1) certificate will expire March 19th, 2010–which is fast approaching. (more…)

UMS Mainframe to be Shut Down

Tuesday, December 1st, 2009

ITS will be shutting down the University of Maine System mainframe as of December 31st, 2009.

Please check the Mainframe End of Service Announcement Page for more information.

Mainframe Retirement: Update for Functional Offices

Friday, October 16th, 2009

Mainframe Shutdown: Update for Student Financials, Student Records, Financial Aid, Admissions, Financials, and Human Resources

Everyone who is or has been a mainframe user needs to mark November 1 on the calendar. (You are or have been a mainframe user if you’ve ever used ISIS, CICS, HRIS, Financier, or Natural, or if you have connected using Hummingbird software or tn3270.) All users of the mainframe should be off by November 1 (except Financial Aid offices, which have additional time).

If you or colleagues have used the mainframe in the past to maintain data sets or statistical programs for research purposes, make sure you are aware of this timeline, and that your data, programs, tapes, or disks are off and converted into a usable format by November 1.

Shutdown Timeline

On October 19, 2009, messages will appear at logon to CMS, CICS, and WebDSIS announcing that ISIS services (including WebDSIS, CICS, and VSE Batch) will be taken down or will be generally unavailable on November 1.

By November 1, 2009, the interface between Mas90 and MaineStreet GL will be ready.

On November 1, 2009, WebDSIS will be taken down. CICS ISIS (CICS1) and VSE batch ISIS libraries will be generally unavailable. Permission may be granted to select campus users to access CICS on a case-by-case basis. Emergency runs of ISIS batch programs may be possible with intervention of ITS staff. HRIS will remain in read-only mode until December 31. WebFAST is unaffected by the mainframe shutdown, and data from 2000-2005 will continue to be available.

Until mid-December 2009, Natural access to all ISIS and Financier data will remain available.

On December 31, 2009, the mainframe will be turned off and all mainframe services cease.

Questions? Contact support@maine.edu.

WebDSIS to be Decommissioned

Friday, October 16th, 2009

As of November 1st, 2009, WebDSIS will no longer be available. The new way for working with the information which used to be accessed there is via MaineStreet.

After December 15th users attempting to access WebDSIS will automatically be redirected to a page  noting the move to MaineStreet for approximately six months. Simplified URLs used to get to WebDSIS such as http://www.maine.edu/dsis will also end up at this page.

16 Central Street Bangor, Maine 04401